Road work is scheduled to begin September 24th on Itawamba and Suqulak Trail. Crews will be milling to a depth of 1.5- 2 inches. The milling process will take 2-3 days for both roads. New asphalt will be installed upon completion of the milling. Expect another 2-3 days for the asphalt work.
Both roads will be open during this time. The contractor will have a flag crew to help direct traffic. Please be safe around the work space.
The association selected the same company that performed the work on the roads last year. We are expecting very good results again.
Updates will continue as we get closer to the start date.