Crews began laying asphalt on Wednesday August 22nd. The entire project is on pace to be completed by the first of next week.
Updated Timeline:
Wednesday 8/22: Completed south side of lodge, and the south east side of main parking lot.
Thursday 8/23: Work space includes east and north side of the lodge.
Friday 8/24: Asphalt to be installed along the front of the lodge(office & tennis court side) and north west corner of lot. Line painting will take place on the east side of the lot.
Monday 8/27: Complete project.
If you don’t have to go to the lodge, please avoid. If you need to stop in, just be aware of where the crews are working. You may need to park in the grass by the baseball field and walk to the lodge doors. If you don’t see fresh asphalt or crews, feel free to drive to the office door.
If you would like to use the beach, please walk from the baseball field or drive your golf cart in the turf to the beach area.
We appreciate your understanding during this project.