Hello,
Milling work is scheduled to be completed on Thursday November 2nd. The final stretch is West Choctaw from the Chickasaw intersection back to the dam.
The asphalt crew is scheduled to begin no later than Monday November 6th. There is a chance they could start Friday, but Mother Nature is just not cooperating. I am seeing more rain in the short range forecast.
The original project end date was November 10th. A&B is going to try to finish as close as possible to that date. Due to the rain, this project may now bleed into the week of the 13th.